Oregon 38 Elk Creek Rapid Bridge Replacement

Time lapse encapsulation. - Slayden Construction, in cooperation with the Oregon Department of Transportation, completed another successful rapid replacement on the OR 38: Elk Creek to Hardscrabble Creek Design-Build Project on September 7, 2008. After months of careful preparation, the process of removing the old bridge, moving the 1220 ton new structure, and re-connecting the highway was performed in only 49 hours (8 hours ahead of schedule). Slayden's excellent safety program insured that everyone working on and visiting the site remained safe on a very congested site.



http://www.youtube.com/watch?v=8dTZIZmLlWs&hl=en